skip navigation

Pouring the Rink Floor

Pouring the Rink Floor

On Friday, June 8th, 2007.. The pouring of the concrete on the Rink floor took place. The frist concrete came out of the trucks around 7:30 am and went non-stop until about 1:30 pm. The 6 hour pour used about ~230 yards of concrete in pouring the 5 inch slab. Each concrete truck holds 10 yards, so there was a bit of action at the pump truck. ** Pics Added 6-17-07 **
https://cdn1.sportngin.com/attachments/photo/0002/8255/06-08-07_Concrete_Pour_-__36_thumb.jpg
  • 06-08-07 Dual Power Trowels
  • 06-08-07 Power Troweling is all thats left
  • 06-08-07 Power Troweling in Action
  • 06-08-07 Hand Level the last few Feet
  • 06-08-07 Concrete all poured
  • 06-08-07 Power Trowel at the Start, Finishing at the far end
  • 06-08-07 Rounding the Final Corner
  • 06-08-07 At the Goal line
  • 06-08-07 Two Cement trucks
  • 06-08-07 Pump Truck setup
  • 06-08-07 Progress
  • 06-08-07 Getting towards the End
  • 06-08-07 Concrete in Action
  • 06-08-07 Pouring at the Edge
  • 06-08-07 Almost Done
  • 06-08-07 Concrete Covering the Pipes
  • 06-08-07 Power Screed in Action
  • 06-08-07 Trowel by Hand
  • 06-08-07 End of the Boxes
  • 06-08-07 2/3's Complete
  • 06-08-07 Working Hard
  • 06-08-07 Water coming to the Surface
  • 06-08-07 Concrete from Truck to Pumper
  • 06-08-07 Leveling
  • 06-08-07 More Pouring
  • 06-08-07 Starting to Level
  • 06-08-07 View from Above
  • 06-08-07 Leveling to edge
  • 06-08-07 Concrete now flowing!
  • 06-08-07 Concrete starting to be pumped
  • 06-08-07 Power Trowels to smooth the floor
  • 06-08-07 Power Screed..Levels the floor by Lasers
  • 06-08-07 Concrete into the Pump Truck
  • 06-08-07 Boom stuck into the rink
  • 06-08-07 Concrete pump truck
  • 06-08-07 Wrapping Removed, Staging Starting to be Removed

Loading…

Pouring the Rink Floor

On Friday, June 8th, 2007.. The pouring of the concrete on the Rink floor took place. The frist concrete came out of the trucks around 7:30 am and went non-stop until about 1:30 pm. The 6 hour pour used about ~230 yards of concrete in pouring the 5 inch slab. Each concrete truck holds 10 yards, so there was a bit of action at the pump truck. ** Pics Added 6-17-07 **